Part 1 GENERAL part 1 general description




Скачать 123.38 Kb.
НазваниеPart 1 GENERAL part 1 general description
страница6/14
Дата конвертации25.10.2012
Размер123.38 Kb.
ТипДокументы
1   2   3   4   5   6   7   8   9   ...   14

DISPOSAL

  1. Dispose of excess excavated material (including rocks and boulders) that cannot be used in construction outside the park.

  2. Unless otherwise specified, all removed material becomes the property of the Contractor and shall be disposed of outside the park.

  3. Immediately remove hazardous rubbish from project site. Place other construction debris in refuse containers at least daily. Dispose of refuse at least weekly, in a legal manner, at public or private dumping areas outside the park. Do not burn or bury refuse inside the park.

  • AIR AND WATER POLLUTION CONTROL

    1. Take all necessary reasonable measures to reduce air and water pollution by any material or equipment used during construction.

    2. Do not dispose of volatile wastes or oils in storm or sanitary drains.

    3. Do not allow waste materials to be washed into streams or bodies of water.

  • PART 4 MEASUREMENT AND PAYMENT


    END OF SECTION


    SECTION 01600


    MATERIAL AND EQUIPMENT


    1. PART 1 GENERAL


    PART 1 GENERAL
      1. DESCRIPTION

        1. The work of this section consists of the general procedures for handling, storing, and protecting material and equipment.

      2. TRANSPORTATION AND HANDLING

        1. Arrange deliveries of materials in accordance with construction schedules; coordinate to avoid conflict with work and conditions at the site. Deliver materials in undamaged condition, in manufacturer's original containers or packaging, with identifying labels intact and legible. Contractor is encouraged to obtain materials in biodegradable or recyclable/reusable packaging which uses the minimum amount of packaging possible.

      3. STORAGE AND PROTECTION

        1. Store all materials in accordance with manufacturer's instructions.

        2. All seals and labels must be accessible for inspection.

        3. Interior Storage: Maintain temperature and humidity within the ranges required by manufacturer's instructions.

        4. Exterior Storage:

    1. Products that are subject to damage by the elements must be stored in weather tight enclosures.

    2. Store fabricated products above the ground, on blocking or skids; prevent soiling or staining. Cover products subject to damage or deterioration with impervious sheet coverings; provide adequate ventilation to avoid condensation.

    3. Store loose granular materials on solid surfaces to prevent mixing with foreign matter.

        1. Protection after Installation: Provide adequate coverings as necessary to protect installed materials from damage resulting from natural elements, traffic, and subsequent construction. Remove when no longer needed.




    1. PART 2 PRODUCTS Not used.


    PART 2 PRODUCTS Not used.

    1. PART 3 EXECUTION Not used.


    PART 3 EXECUTIONS Not used.

    1. PART 4 MEASUREMENT AND PAYMENT


    END OF SECTION


    SECTION 01770


    PROJECT CLOSEOUT


    1. PART 1 GENERAL


    PART 1 GENERAL
      1. DESCRIPTION

        1. The work of this section consists of final cleanup, closeout submittals, and final inspection procedures.




    1. PART 2 PRODUCTS


    PART 2 PRODUCTS
      1. CLEANING MATERIALS

        1. As recommended by the manufacturer of surface to be cleaned.

      2. POSTED OPERATING INSTRUCTIONS

        1. Frame instructions under no glare glass or approved laminated plastic. In areas where operating instructions are subject to sunlight or moisture, provide weather resisting materials.




  • 1   2   3   4   5   6   7   8   9   ...   14

    Похожие:

    Part 1 GENERAL part 1 general description iconDrainage part 1: general

    Part 1 GENERAL part 1 general description iconPart A. General and Academic Information I. General Information Business Address Home Address

    Part 1 GENERAL part 1 general description iconPart 1 General 1 section Includes A. Design, supply, and installation of roof fall protection anchors

    Part 1 GENERAL part 1 general description iconPart 1 General section Includes A. Design, supply, and installation of rigid-rail fall protection system

    Part 1 GENERAL part 1 general description iconPart 1- general 1section includes a. Work of this Section consists of certified and sustainable hardwood and softwood timber, and includes but is not limited to the following

    Part 1 GENERAL part 1 general description iconWeb ct guidelines for using Webct 27-30 Staff Contact Details Academic and Support Staff Contact Details 31-32 part one general information

    Part 1 GENERAL part 1 general description iconСписок литературы. Логика Арно А. Николь П. «Логика как искусство мыслить» П. Б. Струве «Логика для женской гимназии» Асмус В. Ф. «Логика» Москва 1947г. «Формальная логика» лгу 1977г
    «Journal of symbolic logic» 1934г., VI part 4, XXVI part 1-2? 1960 г., V part 4-5, 1980г

    Part 1 GENERAL part 1 general description iconRoe V. Wade (No. 70-18) 314 F. Supp. 1217, affirmed in part and reversed in part

    Part 1 GENERAL part 1 general description iconOrganic Chemistry”,3rd ed., part a (Chapter11) & part B.(Chapter1,2,5,6,7,12)(1993)

    Part 1 GENERAL part 1 general description iconGeneral Description of Local Conditions Covering


    Разместите кнопку на своём сайте:
    lib.convdocs.org


    База данных защищена авторским правом ©lib.convdocs.org 2012
    обратиться к администрации
    lib.convdocs.org
    Главная страница